SPC 1045 - 26   Gallery

 

 

01.05.2013   Production Start
06.05.2013  Setup of latest Battery Technology with online Balancing & Monitoring  
06.05.2013  Engine Testing
16.05.2013  Strip Planking Hulls
30.05.2013  Hull Bottom ready for fairing
05.06.2013 Hull frame
12.06.2013 Build up starts...
16.06.2013 Bulkheads...
20.06.2013 Hull floor
27.06.2013 Interior setup
09.07.2013 Deck  & painting
03.08.2013 Hull with roof
14.08.2013 Gel coat & paint
01.09.2013 Hull finished
 
30.09.2013 Outside work finished

on 08.10.2013 First time in the water
from 10.10.2013 Engines, batteries and solarsystem to be installed
01.12.2013 Engine lifts and cockpit
26.02.2014 Engine testing successfull / Solar System fully operational
February / March - Install final battery system and updated version of engine lifts
The first solar cat is ready to go....

 

 

 